This table shows the total RE capacities (in MW) granted with Feed-in Approvals under the FiT mechanism and which have not yet achieved the FiT Commencement Date.
Installed Capacity (MW) of Plants in Progress |
Year |
Biogas |
Biogas ( Landfill / Agri Waste ) |
Biomass |
Biomass ( Solid Waste ) |
Small Hydro |
Solar PV |
Geothermal |
Small Hydro (low Head) |
Small Hydro (high Head) |
Total |
2021 |
0.00 |
3.40 |
0.00 |
2.50 |
13.00 |
0.43 |
0.00 |
0.00 |
0.00 |
19.33 |
2022 |
0.00 |
50.69 |
21.89 |
20.00 |
52.30 |
0.00 |
0.00 |
0.00 |
0.00 |
144.88 |
2023 |
0.00 |
31.36 |
23.30 |
0.00 |
15.60 |
0.00 |
0.00 |
0.00 |
0.00 |
70.26 |
2024 |
0.00 |
2.70 |
2.40 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
17.42 |
22.52 |
2025 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
200.00 |
207.36 |
407.36 |
Cumulative |
0.00 |
88.14 |
47.59 |
22.50 |
80.90 |
0.43 |
0.00 |
200.00 |
224.78 |
664.34 |
|