This table shows the total RE capacities (in MW) granted with Feed-in Approvals under the FiT mechanism and which have not yet achieved the FiT Commencement Date.
Installed Capacity (MW) of Plants in Progress |
Year |
Biogas |
Biogas ( Landfill / Agri Waste ) |
Biomass |
Biomass ( Solid Waste ) |
Small Hydro |
Solar PV |
Geothermal |
Small Hydro (low Head) |
Small Hydro (high Head) |
Total |
2019 |
0.00 |
6.06 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
6.06 |
2020 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
2021 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
2022 |
0.00 |
3.60 |
0.00 |
0.00 |
29.50 |
0.43 |
0.00 |
0.00 |
0.00 |
33.53 |
2023 |
0.00 |
49.49 |
33.19 |
2.50 |
5.00 |
0.00 |
0.00 |
0.00 |
0.00 |
90.18 |
2024 |
0.00 |
12.46 |
2.40 |
0.00 |
21.60 |
0.00 |
0.00 |
0.00 |
7.82 |
44.28 |
2025 |
0.00 |
51.58 |
31.40 |
11.00 |
0.00 |
0.00 |
0.00 |
124.00 |
90.69 |
308.67 |
2026 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
9.00 |
59.77 |
68.77 |
2027 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
42.00 |
218.05 |
260.05 |
Cumulative |
0.00 |
123.19 |
66.99 |
13.50 |
56.10 |
0.43 |
0.00 |
175.00 |
376.33 |
811.53 |
|