How to Apply for FiA for other RE Installations
The Feed-in Approval (FiA) application steps are as follows:
Step 1
Interested party to check / comply with (check at www.seda.gov.my) :
»
Renewable Energy (Feed-in Approval and Feed-in Tariff Rate) Rules 2011
»
Renewable Energy (Criteria for Renewable Resources) Rules 2011
»
Renewable Energy (Technical & Operational Requirements) Rules 2011
»
Renewable Energy (Renewable Energy Power Purchase Agreements) Rules 2011
»
SEDA Malaysia : RE quota (application based on scheduled FiT Commencement Date)
Step 2
»
Secure legal rights to the site of the RE installation / letter of intent from the site owner
»
Design RE installation (capacity, technical details, etc)
»
Conduct connection confirmation check (CCC) for RE installations > 12 kW and up to 425 kW (to be conducted by the relevant Distribution Licensee).
Conduct power systems study (PSS) for RE installations >425 kW (to be conducted by the relevant Distribution Licensee)
»
Check relevant local authority and other governmental requirements
Issue notice to proceed to service provider/ contractor to commence work
»
Design, install and construct RE installation and interconnection facilities
Step 7
FiT meter installation
Step 8
»
For RE Installations connected through medium or high voltage connections, fulfil conditions to Initial Operation Date & conduct reliability run (to be verified and certified by Qualified Person)
»
For all RE Installations, carry out Acceptance Test (to be verified & certified by Qualified Person)
Step 9
»
FiT Commencement Date
•
Give notice of FiT Commencement Date to SEDA Malaysia & DL before and after FiT Commencement Date
•
Start of FiT duration
Step 10
»
Monthly meter readings
»
DL will issue monthly payment advice to FiA holder after meter is read
»
FiT payment to be paid by DL within 30 days after issuance of payment advice